Below you will find pages that utilize the taxonomy term “Project Tips”
Posts
Quick Post : Workflows not working on a PS2010 farm where the Web Front End Service is disabled
I thought I would post this little gem so I don’t forget it. Hopefully it will be of use to someone else as well.
In the last couple of weeks a few people have told me about issues they encountered running Project Server 2010 workflows on a farm where the web front-end service has been deactivated. Deactivating the service can make sense if you are configuring the farm for improved performance by removing the need to listen to and render pages, or when trying to reduce the attack surface (although this is a lesser concern).
Posts
Project 2013 Quick Start Guide Now Available
Microsoft have just published a number of Quick Start Guides for Office 2013, amongst them is this gem for Project 2013.
The guides themselves are pretty comprehensive and cover not only the feature areas of Project, but also Project Online and the new Reporting and Task path capabilities.
You can grab the the Office 2013 Quick Starts at Download other Office 2013 Quick Start Guides and the Project 2013 specifically at http://office.
Posts
How to create a Windows 8 tile to access Project Server
I thought I would post this for those of you that are upgrading to Windows 8 and wanted to create a simple way of accessing Project Server. In this particular case I am going to show how to pin Project Online, but the same is possible with your on premise Project Server 2013 and 2010 instances.
Pinning from the desktop To start, navigate to your Project Server instance in either Internet Explorer 10 on the desktop.
Posts
Where has Close tasks to update gone in Project Server 2013?
Close Task to update was an interesting feature that was used by the Project Manager to stop the selected tasks from showing up in resource task and timesheet views, therefore stopping users from recording time against those tasks.
In Project Server 2013, the close task to update capability has changed, to leverage a new ‘Locked’ capability which behaves in a similar manner, basically you can choose to lock a task through PWA and once locked and published, the task will no longer show up in the Task and Timesheets views.
Posts
Project Server 2010 / 2013 Preview Setting Comparison
Project Server 2013 introduced a number of changes to where key settings are located throughout the product. Andrew Lavinsky wrote about it earlier this week and stole some of my thunder for this little tool I was putting together.. introducing the Project Server 2010 / 2013 Preview Setting Comparison spread sheet.
The tool maps the various server settings for Project Server 2010, Project Server 2013 On Premise and Project Online all in a handy filtered Excel spread sheet.
Posts
Filtering Projects for Portfolio Selection
A question came up in the Project forums recently around how it was possible to filter the available projects for a portfolio analysis, so I thought I would post a little tip here, which from a majority of the Project Server 2010 implementations I have seen is usually forgotten or managed by business process.
When you create a portfolio analysis, Project Server allows you to choose which projects you want to use as part of the analysis, out of the box, this shows you all the projects currently within the PWA instance, irrespective of their status.
Posts
Windows 8 Release Preview and Project Server 2010
Last week Microsoft released the latest preview of Windows 8, the release preview which you can grab from preview.windows.com. Being a fan of the bleeding edge, I downloaded and installed it onto my slate and have been loving it. However, a number of my colleagues reported that they were having issues using Project Server 2010 with the inbuilt desktop version of IE 10, running into ‘**This Project Server 2010 feature requires at least Microsoft Internet Explorer 7.
Posts
Changing the date format on Gantt chart bars
A while back I posted about how you can change the format of dates in Project. The post showed how easily you could change the format of the dates within the main data entry window of Project. One of my readers pointed out that this was not reflected in the Gantt chart bat text automatically, as you can see below.
Changing the format of these dates is just as simple as changing the other date formats.
Posts
How to ‘Select All’ in the Resource Center
Today I was doing some work in my Project Server 2010 demo image around resources and their associated availability. One thing that kept on getting me was I couldn’t find an obvious way of selecting all of my Enterprise Resources other than clicking on each of the checkboxes individually.
Well after what felt like ten minutes of clicking around, I found how to do a ‘Select All’ on the Resources.
Posts
Three ways to toggle resource over-allocation indicators in Project 2010
Project 2010 introduces a new visual indicator that shows when a resource is over-allocated within the Gantt chart view. This is a great feature that ensures resource over-allocations are front and centre when people view the schedule, instead of being buried away on a resource tab.
However there are times when you may want to suppress these indicators without hiding the whole indicators column, which may contain other important information.
Posts
Make finding Project 2007 commands in 2010 easy
Following on from some of the posts I have been doing about Project 2010, I noticed this spreadsheet from Microsoft this morning that provides a mapping between Project 2007 menu items and where they are in the new Project 2010 fluent interface.
Whilst the new 2010 interface makes it easier to find stuff IMHO, for people that have been using Project 2007 heavily, it may take some getting used to and this spreadsheet will help.
Posts
Where did Copy Picture go?
A couple of people have asked me in the last few days about where the ‘Copy Picture’ icon that used to be front and centre in the Project 2007 had gone in 2010? I know it’s been posted before on other sites and in the newsgroups, but I thought I would repost it again.
To find it, choose the Task tab and then click on the downward arrow next to Copy.
Posts
Project 2010 New File Format
With the Project 2010 client nearing launch, I thought it would be timely to remind everyone who is going to use this fantastic new release that the file format has changed. As such, schedules you create in Project 2010 need to be saved in a previous file version to share with people using Project 2007 and 2003. Luckily Project 2010 makes it really easy to save your schedules in a previous file format.