Inactive Tasks in Project 2010
All too often when you are working on a project, the schedule can evolve from what you originally thought the schedule would be when you built it, to what the reality is. For example, in the schedule below there are three tasks, it turns out that Task 2 is no longer required.
In Project 2007 there are two options to remove the task…
Leave the task on the plan and set the remaining work to 0