Effective Project Management with MS Project : Resource overallocations
Another potential area where errors can creep into project schedules impacting the delivery of a project is that of overallocation of resources. An overallocation is where a resource is assigned more work than they have capacity to complete it. For example, a resource works an eight hour day and is assigned two tasks, each of eight hours effort, both scheduled to occur on the same day as shown below.